Plans / Drawings · Requirement 13 of 27

Vertical sections showing relationships between levels and spaces

Cross and longitudinal sections: basement under the podium, double-height lobby, mezzanine, first floor, five guest floors and the roof venues.

✓ CompliedRC presentation REV09 · p. 115

Answer

Cross and longitudinal sections (R10, attached), coloured by use, showing how the levels and spaces connect. Levels from ground floor +/-0.00: basement -4.50; ground +/-0.00 (double-height lobby to the mezzanine); mezzanine +4.50; first / podium roof decks +8.00; guest floors 2nd-6th +12.00, +16.00, +20.00, +24.00, +28.00 (4.00 m floor to floor); roof venues +32.00; upper roof +36.00; parapets 1.8 m. The basement runs under the whole podium.

Datum: ±0.00 = the normal road level; the hotel ground floor is at road level. Check against the Revit section A-13, which measures from the 2nd floor (0.000): ground -12.000, mezzanine -7.500, 1st -4.000, 2nd 0, 6th +16.000, roof deck +20.000, apex +24.000 – adding 12.00 m gives ground ±0.00, mezzanine +4.50, 1st +8.00, 2nd +12.00, 6th +28.00, roof deck +32.00, upper roof (apex) +36.00, exactly as above. Floor to floor: 4.50 / 3.50 / 4.00 m (dimension chain on A-13); total height about 37.80 m to the top of the roof parapet.

Key data and sources

Each figure with the drawing, study or standard it comes from.

ItemValueSource
DatumGround floor +/-0.00REV09 / R10 drawn
Basement-4.50REV09 / R10 drawn
Guest floor to floor4.00 mREV09 / R10 drawn
Apex+36.00REV09 / R10 drawn
Annex9.0 m clear halls; section to followREV09 / R10 drawn

Drawing evidence – R17 sheets

The latest issued drawings (8 November 2026). Click a sheet to open it full size.

WFY-AR-132
WFY-AR-132Hotel building sections
WFY-AR-133
WFY-AR-133Annex elevations and sections

Where it is in the RC presentation

Wafaiya_Yanbu_RC_Submission_REV09.pdf (135 pages) – click a page to open it full size.

Presentation page 115
Page 115

Evidence photos

The photos attached to this item in the compliance answer sheet.

Evidence photo 1
Photo 1
Evidence photo 2
Photo 2
Evidence photo 3
Photo 3
Evidence photo 4
Photo 4

References

  • R10 Architectural Plans Y5S-AR-SC-01 (A-13 cross / longitudinal sections); WFY key data levels